Work continued this week: 

• Nose bay door seals replaced

• Wiring inspections completed

• RTI inspections carried out

• Rotor head damper bolts replaced IAW RTI

• Aircraft alignment checks carried out

• Environmental control system Teleflex locked and split pinned

• No.2 ECL range adjusted and locked

Work to be continued next week: 

• Inertia crash switches test cables to be investigated.

• Transponder/Radio annual to be carried out.

• Aircraft bonding check to be carried out.

• AFCS testing

• No.1 ECU anti-det run