No.1 ECU Fitted

Work continued this week:

• ECU Pre-installation checks carried out.
• ECU bay cleaned and pre-installation checks carried out
• No.1 ECU fitted to aircraft.
• Exhaust assembly fitted to No.1 engine
• Panels for rear of aircraft around exhausts refitted
• Port and starboard upper intakes rubbed down and prepped for painting
• Port lower intake prepped and fitted to aircraft
• Gearbox dish mounts fitted
• Paperwork brought up to date and independent checks carried out

Work to be continued next week:

• Fit upper intakes once painted
• Test anti-icing heater mats port and starboard
• Investigate pitot leak

twentytwopl 20 November 2020 Uncategorised