No.1 and 2 ECU’s refitted

Work continued this week:

• No.1 and 2 ECU’s removed.

• 2x stub shafts changed for serviceable components with life details

• No.1 and 2 ECU’s refitted

• Calibrated pitot static instruments retrieved and batched in ready for fitting

Work to be continued next week:

• Cabin doors to be refitted

• Mic/tel lead mount to be fitted

• Nose compartment seals to be changed

• Start fitting calibrated instruments