Newly arrived blades from Everett’s unloaded

Work continued this week:

XZ179:

• Newly arrived blades from Everett’s unloaded

• Blades cleaned and inspected externally, potentially serviceable blades put to one side

• Anti node weights removed from potentially serviceable blades, cleaned,
inspected, refitted and re-sealed.

XZ678:

• Tail rotor gearbox removed

• Tail rotor servo mounting plate removed, cleaned and inspected

• Tailplane removed

• Tail fin section cleaning begun, inspections carried out as cleaning progresses

• Tail rotor driveshaft NDT’s carried out.

Work to be continued:

XZ179:

• Finish inspection of potentially serviceable blades.

• Investigate Barometric Altitude Hold light.

XZ678:

• Continue cleaning and inspection of tail fin section.

• Begin cleaning and inspection of tail boom.

twentytwopl 8 March 2022 Uncategorised