Work continued this week:

  • Main rotor head rigging carried out. Adjustment of the pitch links, fore and aft and lateral control rods.
  • Control system position indicators set up.
  • Cockpit voice recorder fitted.
  • P1 and P2 seats refitted.
  • AFCS and ASE testing and fault finding started.

Work to be continued next week:

  • In depth AFCS and ASE system testing.
  • Testing compass system with ASE system.