Aircraft de-jacked after alignment checks

Work continued this week: 

• Aircraft de-jacked after alignment checks 

• Aircraft prepared for ground running 

• AFCS system fault finding/testing 

• Ground run carried out 

• Replacement controller engaging ordered 

• MRH spider arm wear check carried out 

• Crash switches test looms started to be made 

Work to be continued next week: 

• Aircraft bonding check to be carried out

• Seal nose bay door seals with PRC when delivered 

• Environmental control system to be inspected/tested

twentytwopl 27 September 2021 Uncategorised