First Two Hovers Carried Out Successfully
Work continued this week:
XZ179:
- Ground runs carried out for tracking of main and tail rotor blades
- Lateral vibration and blade track corrected to allow hover tests
- First two hovers carried out successfully
- Investigating hydraulic cooling fan fault
- Post first flight inspections carried out
Work to be continued in the new year:
XZ179:
- Continue tracking of main rotors
- More hover checks to be carried out
- Organise compass swing
- Sort any snags