First Two Hovers Carried Out Successfully

 Work continued this week: 

XZ179: 

  • Ground runs carried out for tracking of main and tail rotor blades 
  • Lateral vibration and blade track corrected to allow hover tests 
  • First two hovers carried out successfully 
  • Investigating hydraulic cooling fan fault 
  • Post first flight inspections carried out 

Work to be continued in the new year: 

XZ179: 

  • Continue tracking of main rotors 
  • More hover checks to be carried out 
  • Organise compass swing 
  • Sort any snags 

twentytwopl 23 December 2021 Uncategorised